Kyrgyzstan Sets New Electricity-Based Fees for Mining, Data Centers and AI Firms in Naryn SEZ

Photo: kyrtag.kg
FTZ News: The government has set new fees for data centers, cryptocurrency miners and artificial intelligence companies operating in the Naryn Free Economic Zone.
Under a resolution signed Nov. 6 by Cabinet Chairman Adylbek Kasymaliev, those businesses will pay nothing in their first year of commercial operation. The rate rises to 1.5% of electricity costs in the second year and 3% from the third year on. The fee is calculated on actual power used, measured by meters and priced at the tariff the Cabinet sets for energy-intensive commercial users.
The new structure comes with a condition. Companies must generate their own electricity or import it. They cannot draw power from the national grid.
Other businesses in the zone remain subject to the existing 1% fee, calculated on revenue from goods and services sold in Kyrgyzstan or exported abroad. The new rules amend a 2014 regulation that governs the zone.
The change comes as Kyrgyzstan courts large projects in Naryn. On Nov. 7 the government signed an investment agreement with StarOcean Investment LLC for a 200-hectare industrial park inside the zone. Plans call for data centers, AI computing infrastructure and low-carbon manufacturing. A separate data center for state use is also planned.
Construction of a new substation serving the industrial park began in March. The 110-kilovolt Kur-Terek facility includes a 10.4-kilometer transmission line and is expected online by the end of the year. Officials have not said how the substation will interact with the independent-power requirement for the high-tech residents.